  试题1


  A project is completed and customer approval is obtained.Th e IT department plans an unscheduled audit of the project.W hat should the project manager do


  项目已完成并获得客户批准,IT部门计划对项目进行不定期审计。项目经理应该怎么做


  A、Review company policies and notify the stakeholders involved审查公司政策并通知涉及的项目相关方。


  B、Allow the audit as it could provide more value for the project允许审计,因为可以为项目提供更多价值。


  C、Requests to review of the IT Department's quality assurance policies请求审查IT部门的质量保证政策。


  D、audit is not part of the quality management plan Review company policies and notify the stakeholders involve告知项目发起人IT审计不是质量管理计划的-部分。Advise the sponsor that an IT


  试题参考答案:B


  试题2


  项目经理计算出当前PV=10000美元,AC=12000美元,S PI=1.3。项目经理由此计算CPI,下列说法正确的是∶


  A、CPI>1,成本超支


  B、CPI<1,成本未超支


  C、CPI<1,SPI>1,进度正常


  D、CV=1000,项目未超支


  试题参考答案:D


  试题3


  与项目团队一起,项目经理发现了可以实施快速跟进的两项工作,即在任务A开始1天后就开始实施任务C,从而使任务C与任务A并行实施3天。这种做法对项目完工日期有什么影响?()


  A、项目将提前2天完成


  B、关键路径将改变


  C、项目将提前1天完成


  D、项目将提前3天完成


  试题参考答案:D


  试题4


  During a project's user acceptance stage,some user's comp lain that their expectations have not been met.What should t he project manager have done differently?


  在一个项目的用户验收阶段,一些用户抱怨他们的期望未得到满足,项目经理事先应该采取哪一个不同做法?


  A、Considered stakeholder feedback考虑相关方的反馈


  B、Conducted risk assessments执行风险评估


  C、Implemented conflict management techniques实施冲突管理技术


  D、Establish a professional relationship with the users与用户建立一种专业关系


  试题参考答案:A


  试题5


  Although the stakeholders thought there was enough money in the budget.,halfway through the project the cost performance index(CPI)is 0.7.To determine the root cause,several stakeholders audit the project and discover the project cost budget was estimated analogously.Although the activity estimates add up to the project estimate,the stakeholders think something was missing in how the estimate was completed.Which of the following describes what was missing?


  虽然项目干系人认为预算已经足够了,但是项目进行到一半时,成本绩效指数(CPI)为0.7。为了找出原因,几名项目干系人审计该项目,发现该项目的成本预算是用类比估算法作出的。虽然项目估算是活动估算累加得出的,但是项目相关方认为估算时忽略了一些东西。下列哪项是忽略的内容?()


  A、Estimated costs should be used to measure CPI.


  应使用估算成本衡量成本绩效指数(CPI)


  B、SPI should be used,not CPI.


  应使用进度绩效指数(SPI),而不是成本绩效指数(CPI)


  C、Bottom-up estimating should have been used.


  应使用自下而上估算法


  D、Past history was not taken into account.


  未考虑历史数据


  试题参考答案:C